Dear All,

Please help with this, a lot is at stake!

I have about 48 Free Standing Units to be installed each of 8.0TR capacity. The units are arriving in 2 days.

The refrigerant piping has been done. The pipes passed through sleeves in the wall. The plastering is done and there is no more provision for extra pipes.

Just now, I discovered that the units that are arriving are all Double Circuit Units! Is it possible to merge the pipes after the ODU and split them again before entering the IDU? What would be the effect on the machine? Any extra measures to be taken before attempting this?

Please share your experience and insights. I shall be forever indebted to you.