Results 1 to 5 of 5
Thread: Hazardous waste certificates
-
22-03-2012, 11:09 PM #1
Hazardous waste certificates
Chaps
do you produce a TWC certificate every time you recover refrigerant in duplicate as per the regs?
-
22-03-2012, 11:16 PM #2
Re: Hazardous waste certificates
Oh yes and your good self ?
Brian - Newton Abbot, Devon, UK
Retired March 2015
-
22-03-2012, 11:18 PM #3
Re: Hazardous waste certificates
Climate centre will not collect from site without one
but I do know one that will, I dont use them of course
R's chillermanIf the World did not Suck, We would all fall off !
-
23-03-2012, 12:09 AM #4
Re: Hazardous waste certificates
Is this a waste transfer ticket?
Am looking into getting some printed (along with some f gas log books...)
At pressent it gets put on work sheet, unit serial number, bottle number ref type etc etc, and a transfer note when the cyclinder goes back to whoever i gots it from! Also its duplicated in my work diary.Mostly found in Oxfordshire, UK :)
-
23-03-2012, 07:01 AM #5
Re: Hazardous waste certificates
This is what we do as it's all built within our jobsheets. I was looking round late last night and was concerned that we neededto fill out those complex TWC from dept of Enviroment.
However I found this on ACRIB
1) One-Off Recovered Refrigerant Removal Operation
You can remove recovered refrigerant as a one-off operation, servicing aspecific site – recover refrigerant, remove it from the site and transfer it toa wholesaler, refrigerant distributor or reclaimer. If you are removing lessthan 500kg from that site in any 12 month period, you do not require aPremises Code for that site but –
a) You must keep any recovered refrigerant from that site totallyseparate from any other recovered refrigerant and transfer it to a wholesaler,distributor, or reclaimer as a totally separateconsignmentof recovered refrigerant – It must not be placed in cylinders with recoveredrefrigerant from other sites.
b) You must keep a detailed record of all the hazardous waste, includingrecovered refrigerant removed by you or any other person from thatspecific site in any 12 month period and if the amount you intend to remove islikely to reach or exceed 500kg -
You (or the site owner) must obtain a Premises Code for that specificsite before you remove any further recovered refrigerant that amounts to500 kg or more of the total 12 month Hazardous Waste removal inventory for thatsite.