Results 1 to 22 of 22

Thread: how long??

  1. #1
    DavidF1's Avatar
    DavidF1 Guest

    how long??



    Hello... I could do with a little info from those in the know!!!!

    How long would you allow to pipe-up 10 ceiling cassette units

    Ceiling grid in place (Grrrr)

    The usual M&E obstacles above grid + ceiling suspension wires

    pipe 5/8 and 3/8 Hard drawn copper

    first fix pipework already in place, although they terminated a bit too far away from cassette locations most have to be extended approx 600mm to 2.5m. 2-3 bends per run.

    Swage one end of pipework and flare the other end

    Connect swaged end to already installed pipework and braze joint

    tighten flare connections to cassette

    Working off stepladder , not platform

    Many thank yous if you can help..


    David



  2. #2
    Join Date
    Oct 2007
    Location
    manchester
    Age
    50
    Posts
    5,639
    Rep Power
    45

    Re: how long??

    if the cassettes are fitted in the grid then 14hrs to do all 10 once youve got ur gear/pipe in the area
    (not blowing me own trumpet)
    why wasnt the pipework long enough in the 1st place
    Last edited by install monkey; 16-09-2011 at 11:43 PM. Reason: missed the point that some pipework was 2.5m too short!!

  3. #3
    Join Date
    Apr 2010
    Location
    england
    Age
    51
    Posts
    295
    Rep Power
    15

    Re: how long??

    if installing from scratch no holes cut nothing in place 3 days per unit as yr doing it with pipe in 2 max personally if you havent installed units before go back to the 3 as you will find somat that dont fit right or work and commisioning can take a while if things is a pain lol
    I can fix broke but I cant fix stupid :)

  4. #4
    Join Date
    Aug 2006
    Location
    england
    Age
    50
    Posts
    3,856
    Rep Power
    46

    Re: how long??

    Think i'd allow 1.5/2 hours each, though it would depend on what level they want you to work to, things like nitrogen while brazing would take longer to set up.

    I find often that people want things priced and timed like its thrown in but installed by the book and you have to find a level somewhere between.
    Mostly found in Oxfordshire, UK :)

  5. #5
    Join Date
    Apr 2010
    Location
    england
    Age
    51
    Posts
    295
    Rep Power
    15

    Re: how long??

    Quote Originally Posted by install monkey View Post
    if the cassettes are fitted in the grid then 14hrs to do all 10 once youve got ur gear/pipe in the area
    (not blowing me own trumpet)
    why wasnt the pipework long enough in the 1st place
    14hrs jeeeeeeeeeeeeeezzz ya doin ya self out of overtime lol 10 units if it was just to make final conections you need a day or 2 to finish pipes off and a day to put them all under pressure then a day to vac them all and maybe a day to commission and do all paperwork and chat up office dollies lol
    I can fix broke but I cant fix stupid :)

  6. #6
    Join Date
    Oct 2007
    Location
    manchester
    Age
    50
    Posts
    5,639
    Rep Power
    45

    Re: how long??

    monkeys make the best installers-swinging from ladders and grunting!!!

  7. #7
    Join Date
    Apr 2010
    Location
    england
    Age
    51
    Posts
    295
    Rep Power
    15

    Re: how long??

    Quote Originally Posted by monkey spanners View Post
    Think i'd allow 1.5/2 hours each, though it would depend on what level they want you to work to, things like nitrogen while brazing would take longer to set up.

    I find often that people want things priced and timed like its thrown in but installed by the book and you have to find a level somewhere between.
    buy the book would be a long time lol did 10 splits before christmas wall mounts nothing in place isolators were fitted by sparks 20 days i was given did them in 18 but had holes cut 65mm by third party as it was reinforced concret rsj to drill through took guy 10 days to cut them all think we did good all running when we left job
    oh and no overtime at all 18 standard days with overtime could have done it in 10 maybe
    Last edited by simon@parker; 17-09-2011 at 12:07 AM.
    I can fix broke but I cant fix stupid :)

  8. #8
    Join Date
    Oct 2007
    Location
    manchester
    Age
    50
    Posts
    5,639
    Rep Power
    45

    Re: how long??

    10 spits-not splits! haha
    Quote Originally Posted by simon@parker View Post
    buy the book would be a long time lol did 10 spits before christmas wall mounts nothing in place isolators were fitted by sparks 20 days i was given did them in 18 but had holes cut 65mm by third party as it was reinforced concret rsj to drill through took guy 10 days to cut them all think we did good all running when we left job

  9. #9
    Join Date
    Apr 2010
    Location
    england
    Age
    51
    Posts
    295
    Rep Power
    15

    Re: how long??

    Quote Originally Posted by install monkey View Post
    10 spits-not splits! haha
    am half way down bottle of jack so think i spelling quite well :P lol hahahahahahahahaahaha changed it :P
    I can fix broke but I cant fix stupid :)

  10. #10
    Join Date
    Oct 2007
    Location
    manchester
    Age
    50
    Posts
    5,639
    Rep Power
    45

    Re: how long??

    is that a spin off of 1 man and glass-not going there haha

  11. #11
    Join Date
    Apr 2010
    Location
    england
    Age
    51
    Posts
    295
    Rep Power
    15

    Re: how long??

    Quote Originally Posted by install monkey View Post
    is that a spin off of 1 man and glass-not going there haha
    errrrrrrrrrrrrrrr no have heard bout that and no way ever :P that would be jack daniels fine whisky the good stuf but am home with a laptop filling this thread and the only glass involved is full of JD and coke off topic lol
    I can fix broke but I cant fix stupid :)

  12. #12
    Join Date
    Mar 2001
    Location
    ireland
    Age
    53
    Posts
    1,450
    Rep Power
    41

    Re: how long??

    Right back from my refreshments, DavidF1, before i quote are you installer or customer?

    al
    Mostly found in the southern part of this green and pleasant land.

  13. #13
    Join Date
    Apr 2006
    Location
    UK
    Age
    55
    Posts
    1,908
    Rep Power
    30

    Re: how long??

    Quote Originally Posted by al View Post
    Right back from my refreshments, DavidF1, before i quote are you installer or customer?

    al
    Morning Al

    hope you enjoyed your refreshments & will be interesting for me and the original poster, what your times would be, mine would be the longest somewhere past simons but (takes me half a day to get in rythem with lamp thats only used a few times a year) 'Install's 14hrs sounds like bogit & scarper to me (sorry install) surely it can not be done in that time properly, but he does use his lad so are you quoting one set or two sets of hands here

    @simon JD one of my favourites

    R's chillerman
    If the World did not Suck, We would all fall off !

  14. #14
    Join Date
    Mar 2001
    Location
    ireland
    Age
    53
    Posts
    1,450
    Rep Power
    41

    Re: how long??

    Afternoon CM, i'd normally allow a day and a half per unit, man and mate, some slower, some faster, anyone looking for an install today after this mornings rugby would be waiting til Tuesday to see an indoor hung!!

    al
    Mostly found in the southern part of this green and pleasant land.

  15. #15
    Join Date
    Oct 2007
    Location
    manchester
    Age
    50
    Posts
    5,639
    Rep Power
    45

    Re: how long??

    the reason i can pipe like a maniac is because i flare first time everytime!!!! also mini me slows me down because i throw small weighty objects at him when his bird is texting-usually 10x30 cone pointss as they are pointed,and u can carry a few in ur pocket!

  16. #16
    DavidF1's Avatar
    DavidF1 Guest

    Re: how long??

    Well thanks for all the replies...
    The 1st fix pipework was installed by others and for various reasons the cassettes ended up in slightly different places compared with what was planned.
    I’m an Installer, not a customer... Or rather an installer assisting an installer who thinks I too slow.
    I piped up 8 units in 14 hours (average 1.75h each) and apparently they can be done in 30 mins each!!!!!!!
    Needless to say it was reassuring to see some of the replies, especially the one that said 1.5-2h per unit.
    Right pain in the bum trying to fit with grid in place, even where there was enough pipe length left behind, because of all the ‘horizontal’ obstacles and it being hard drawn copper it is not possible to insert bends in situ.

  17. #17
    Join Date
    Mar 2001
    Location
    ireland
    Age
    53
    Posts
    1,450
    Rep Power
    41

    Re: how long??

    Fair going David, funny how it can always be done quicker by the guy paying the bill!!

    al
    Mostly found in the southern part of this green and pleasant land.

  18. #18
    Join Date
    Oct 2007
    Location
    jersey channel islands
    Posts
    186
    Rep Power
    19

    Re: how long??

    iwondered why you were using hard drawn , soft drawn would be better to use ? as could be bent in situ thru grid with hydralic benders .
    i too love it when the guy paying tells me how long it will take .
    and the time to purge as well.
    some forget they are paying for a engineer , not just some bloke , a engineer who has trained and learnt to do this work to a good standard , and the units will give good service for years to come .
    good work is not cheap and cheap work is not good imho.

  19. #19
    Join Date
    Mar 2001
    Location
    ireland
    Age
    53
    Posts
    1,450
    Rep Power
    41

    Re: how long??

    "good work is not cheap and cheap work is not good imho.2

    Damn right!

    al
    Mostly found in the southern part of this green and pleasant land.

  20. #20
    Join Date
    Apr 2006
    Location
    UK
    Age
    55
    Posts
    1,908
    Rep Power
    30

    Re: how long??

    Quote Originally Posted by DavidF1 View Post
    Well thanks for all the replies...
    The 1st fix pipework was installed by others and for various reasons the cassettes ended up in slightly different places compared with what was planned.
    I’m an Installer, not a customer... Or rather an installer assisting an installer who thinks I too slow.
    I piped up 8 units in 14 hours (average 1.75h each) and apparently they can be done in 30 mins each!!!!!!!
    Needless to say it was reassuring to see some of the replies, especially the one that said 1.5-2h per unit.
    Right pain in the bum trying to fit with grid in place, even where there was enough pipe length left behind, because of all the ‘horizontal’ obstacles and it being hard drawn copper it is not possible to insert bends in situ.
    Sounds like hard work mate, especially as all above head, i like to connect units up and work backwards to condensor, but not done one for nearly 20 years and that was all rolled soft copper, would not fancy doing it all in tube, slit the wrists time

    R's chillerman
    If the World did not Suck, We would all fall off !

  21. #21
    Join Date
    Apr 2011
    Location
    England
    Age
    35
    Posts
    41
    Rep Power
    0

    Re: how long??

    Going a bit off topic but I'm an installer who has 5 years experience in my first year i was told to never flare hard drawn pipe as its more prone to leaks.

    Agree? Disagree?

  22. #22
    Join Date
    Mar 2001
    Location
    ireland
    Age
    53
    Posts
    1,450
    Rep Power
    41

    Re: how long??

    never had an issue with it, was always told to heat it first.


    al
    Mostly found in the southern part of this green and pleasant land.