Brine system.
Hi all.
I am trying to work out the capacities for two bare tube evaporators cooling a brine solution.
Galvanized tubing is being used for the evaporators.Tube diameter is 1 1/4".
Each evaporator has 83.5 feet in total pipe length.
3.14159X1.25=3.927
3.927X1002=3934.854 sq.in
27.325 sq.ft of pipe surface per evaporator.
Evaporation temp would probably be about -10 c when at temperature.
Brine solution will be about 1-2 c when at temp.
Refrigerant is R 409a.
I am trying to get a capacity so I can match a compressor to this application.
Any help would be appreciated.
Regards.
Similar Threads
-
Daikin fault codes
By Chris2005 in forum Air ConditioningReplies: 45Last Post: 21-03-2012, 10:09 PM -
System Burn Out Troubleshooting
By altaf22m in forum Technical DiscussionsReplies: 13Last Post: 07-05-2010, 09:24 AM -
automating a chilled brine refrigeration system using ammonia refrigerant
By luciom in forum IndustrialReplies: 29Last Post: 02-10-2008, 09:48 PM -
Burn out System, Clean up procedure. & Troubleshooting.
By altaf22m in forum CommercialReplies: 19Last Post: 15-04-2008, 07:03 PM -
Refrigeration system proposal; comments please.
By DaBit in forum Technical SpeculationsReplies: 13Last Post: 01-01-2003, 03:42 PM