Hi everyone, any suggestions on starting up above machine after not moving for
two years and moved to new installation?
Printable View
Hi everyone, any suggestions on starting up above machine after not moving for
two years and moved to new installation?
Hi and welcome to the forum.
What exactly is your MTA Phoenix as a web search brings up a lot of different items under that title. Is it a chiller, a bus or anything similar?
Hi Brian, it could very well double as a bus :-)
Air cooled 6 stage water chiller - make/model: MTA RAB782
Strange scenario as this is just a temperory installation:
Machine draws in excess of 600A at full load but client only has 200A available.
It is a trial-run and only 20% of full capacity will be needed. I understand that the
delivery capacity can be limited in the controller.
What I mostly need to know is..how to perform a pre-inspection and what to look out for.
Any input will be greatly appreciated.
Cheers!